CPC Expansion – Building Project


CPC BUILDING NEWS 2026 – CPC is beginning construction now on the Building Addition (Sanctuary)!
Watch the progression of the build – click on this link to see the most updated image in real time!
Planned Building Schedule
- April 22-24: Precast Panels installed
- April 28 – May 6: Structural Steel installed
- May 7-20: Roof installed
- May 21-22: Under-floor Conduit installed
- May 27-28: Floor Slab poured
- June 3 – August 21: Interior (HVAC system, framing, drywall, lighting, etc.)
- August 28 – September 3: Interior Painting
- August 28 – September 10: Flooring & Outside Landscaping
- September 11-24: Stage Lighting Set Up
Building Fund
Construction has begun on our new Sanctuary! We are receiving donations and pledge fulfillments now toward the Building Project.
To save the Church 2.7% on credit card fees, please consider giving by e-check from your bank, or by a personal check. If not possible, donations and pledges may also be fulfilled through our easyTithe Giving Page! Click the Button below! Thank you!