Planned Building Schedule

  • April 22-24: Precast Panels installed
  • April 28 – May 6: Structural Steel installed
  • May 7-20: Roof installed
  • May 21-22: Under-floor Conduit installed
  • May 27-28: Floor Slab poured
  • June 3 – August 21: Interior (HVAC system, framing, drywall, lighting, etc.)
  • August 28 – September 3: Interior Painting
  • August 28 – September 10: Flooring & Outside Landscaping
  • September 11-24: Stage Lighting Set Up